Progress Payments for a Renovation in NZ: How They Work

Writer: Rudi Visser
Rudi Visser
2 days ago
10 min read

Homeowner and builder review renovation progress claim

A progress payment is a payment you make in stages as renovation work is completed, instead of paying everything at the start or the end. In New Zealand the law gives builders the right to claim them, and it sets rules for what the contract and each invoice must contain. The safest way to handle them is to agree the stages, amounts and due dates in writing before work starts, then pay each claim against work you can see. Our approach is a fixed-fee contract with an agreed scope and price, managed through one point of contact, so every payment ties back to a clear scope.



TL;DR

 

  • A progress payment is a staged payment for work done. It is different from a deposit (paid before work starts) and from the final payment (paid at completion).

  • For residential building work of $30,000 or more including GST, a written contract is mandatory and must set out the number of payments, the interval, each amount, each due date and how payments are invoiced, made and receipted.

  • Unless your contract says otherwise, a formal payment claim is due 20 working days after it is served on you.

  • If you disagree with a claim, respond in writing within the deadline with the amount you will pay and your reasons. Do not simply stop paying.

  • Keep enough money unpaid to finish the job if something goes wrong. That is the whole point of paying in stages.

 

Table of Contents

 

 

What progress payments are, and how they differ from a deposit

 

A renovation payment plan usually has three kinds of payment:

 

  1. Deposit. Paid before work starts. It covers early costs such as plans, consents, site set-up or ordering materials.

  2. Progress payments. Paid at agreed stages or intervals, each for work completed up to that point.

  3. Final payment. Paid when the job is finished and you have checked it.

 

Under the Construction Contracts Act 2002 (the CCA), a party who has agreed to carry out construction work has the right to progress payments. The Act works out each payment from the period it covers, the value of the work carried out or still to be carried out, and any contract terms such as retention (money held back until the job is done) or liquidated damages (an agreed sum for delays). The CCA also cannot be contracted out of, so a clause that tries to remove your rights or the builder’s will not stand.

 

In plain terms: you pay for work done, the builder is entitled to be paid as the job moves along, and both sides can see how each figure was reached.

 

What your contract must say about payments

 

A written contract is mandatory for residential building work costing $30,000 or more including GST, according to MBIE’s homeowner guide (MBIE is the Ministry of Business, Innovation and Employment, which administers building law). It is recommended for any size of job, and MBIE’s overview of the building process advises you to be clear on exactly what you will pay and when.

 

For contracts at that $30,000 level, BRANZ explains that the Building (Residential Consumer Rights and Remedies) Regulations 2014 require the contract to include:

 

  • the number of payments

  • the interval between payments

  • the amount of each payment

  • the date each payment is due, and how these are worked out

  • how payments will be invoiced, made and receipted

 

Before you sign, the contractor must also give you a disclosure statement (skills, qualifications, licensing, insurance and guarantees) and the consumer protection standard checklist. The contract should also cover how defects will be fixed, how disputes are resolved and how variations (changes to the agreed work) are agreed before work continues.

 

If a contract you are offered leaves the payment section vague, ask for it to be written out before you sign. A payment section that says only “payment on invoice” gives you nothing to check an invoice against.

 

Tying payments to stages

 

The CCA allows a single payment or several progress payments, so the structure is up to you and the contractor. Two common ways to set it up:

 

  • Stage-based: a payment when a defined stage is finished, such as demolition and strip-out complete, rough-in plumbing and electrical complete, linings and waterproofing done, fit-out complete.

  • Time-based: a payment on a set date each fortnight or month for work done in that period.

 

For a kitchen or bathroom, stage-based is usually easier for a first-time renovator to check, because you can see for yourself whether the cabinetry is installed or the tiling is finished. If you are unsure what the stages look like in order, our renovation sequencing roadmap sets out the five stages most NZ renovations follow.

 

The deposit: how much is reasonable

 

Master Build, an industry body for builders, says in its homeowner guide that a deposit should typically be no more than 10% of the residential build cost. The same body says its loss-of-deposit cover applies until permanent building work starts, with the deposit funding preliminary work such as plans, consents, site set-up or materials.

 

A 10% deposit is a sensible ceiling to hold in mind when you read a quote. A large upfront payment leaves you with less money in hand if the project stalls.

 

A worked example

 

This is an illustration, not a quote. Suppose a bathroom renovation contract is $30,000 including GST. A payment schedule might look like this:

 

Stage

What you can check

Payment

Running total

Deposit

Contract signed, consent and materials ordered

$3,000 (10%)

$3,000

Strip-out and rough-in complete

Old fittings gone, plumbing and electrical roughed in

$9,000

$12,000

Waterproofing and linings complete

Walls lined, membrane applied

$6,000

$18,000

Tiling and fit-out complete

Tiles, vanity, shower, toilet installed

$9,000

$27,000

Final payment

Walk-through done, defects list agreed

$3,000

$30,000

Two things make this schedule work for you. Each payment is smaller than the value of the work still to come, and a final payment is held until you have walked through the finished job. If the contractor stopped after stage two, you would still have $18,000 of the contract price unpaid to bring someone else in. That is the logic Master Build gives for a payment schedule: you pay for completed work and keep enough to finish the job with someone else if something goes wrong.

 

What a payment claim must include, and when you must pay

 

A payment claim is the formal request for payment. Many everyday invoices are simpler, showing the work completed, the amount due, GST and the date payment is required. A claim made under the CCA has to meet more requirements. Under section 20 of the Act, it must:

 

  • be in writing

  • identify the contract, the work and the period it covers

  • state the amount claimed and the due date

  • show how the amount was calculated

  • state that it is made under the Act

  • come with a written outline of the response process and what happens if you do not respond or do not pay (this is the prescribed Form 1)

 

If your contract does not set a different date, the payment becomes due 20 working days after the claim is served on you. Legal 500’s 2026 NZ construction guide describes this as the default where a contract is silent. It also notes that conditional payment terms, such as “pay when paid”, are prohibited.

 

When an invoice arrives, check it against the contract in this order:

 

  1. Is the stage or period it covers one the contract lists?

  2. Does the amount match the schedule, plus any variations you approved in writing?

  3. Is the work actually finished, and does it look right?

  4. Is GST shown correctly?

  5. Is the due date the one in the contract?

 

If all five match, pay on time. Paying promptly keeps the job moving and your relationship with the crew on good terms.

 

If you disagree with a claim

 

Sometimes a claim comes in for work that is not finished or has defects. The CCA gives you a structured way to respond, and it is worth knowing before you ever need it.

 

Under section 21, you can reply with a written payment schedule. It states the amount you will pay. If that is less than the claimed amount, it must show your calculation and your reasons, including any reason for withholding. Section 17 allows the value of the work to be reduced by the estimated cost of fixing defective work, so a genuine defect is a valid reason.

 

Two practical points:

 

  • Respond within the deadline. If you miss the response deadline (the time in your contract, or 20 working days) and then do not pay by the due date, sections 22 to 24 allow the contractor to recover the unpaid amount plus reasonable recovery costs as a debt, and to give notice of intention to suspend the work.

  • Do not just stop paying. MBIE’s guide advises putting your concerns about an invoice in writing to the contractor, and warns that simply withholding payment may make things worse because the contractor could start dispute resolution.

 

Pay the part you do not dispute, explain the rest in writing, and keep photos and dates of the work in question.

 

Where a dispute goes next

 

MBIE’s guide says to follow the dispute resolution process in your contract first. After that, claims up to $30,000 can go to the Disputes Tribunal, and larger claims go to the District Court. If a contractor did not give you the required contract documents, you can complain to MBIE, and the penalty can be a fine of up to $2,000. Consumer NZ also notes that for building work over $60,000 the written contract should set out how disputes are resolved, and that default Building Act clauses on subcontractors, disputes and notices apply automatically to residential building agreements.


Dispute routes and key renovation contract thresholds

If you have a legal question about your own contract, a lawyer is the right person to ask. Community law centres and the Disputes Tribunal’s own information are the usual starting points for smaller claims.

 

Your protections after the final payment

 

Paying the last invoice does not end your rights. According to MBIE’s guide, you have an automatic 12-month defect repair period in which the contractor must fix defects you report in writing. You can also take action within 10 years of completion if the Building Act’s implied warranties are not met, even when they are not written into your contract. Our guide to what building warranties in NZ actually protect you from explains how these work in practice, and what to check on renovation insurance covers the cover your contractor should hold.

 

Set a defects list at the final walk-through and put it in writing. Hold the final payment until it is agreed.

 

Has anything changed recently?

 

The core payment rules are stable. The CCA, as amended in 2015, still sets the 20-working-day default and the payment schedule response process. MBIE’s guide, last published in November 2025, confirms the $30,000 written contract threshold, the 12-month defect period, the 10-year implied warranties and the Disputes Tribunal limit of $30,000. Thresholds can change, so check the MBIE page for the current figures before you sign.

 

Why a single, fixed-fee contract makes payments easier

 

Progress payments get messy when a job has several trades, each invoicing separately and on their own terms. You end up checking five invoices against five scopes. The cleaner setup is one contract, one agreed price and one payment schedule, with one person you ask when something does not add up. Our guide on coordinating trades on a renovation covers how that works across plumbing, electrical, building and finishing.

 

Our view on paying for renovation work

 

Most payment problems we hear about start before the first invoice. The scope was loose, so nobody could say whether a stage was finished.   Our work is built around fixed-fee quotes and a single point of contact. We coordinate all the licensed trades and handle the building consent process, so the scope you sign is the scope that gets built and the price is the price you agreed.   When you can point to a stage and say whether it is done, a progress payment is a simple decision. Our advice to any first-time renovator is to insist on a written schedule tied to visible stages, keep a deposit modest, and hold the final payment until the walk-through.   That is the standard we want our own projects measured against.   Rudi

 

Renovating in Auckland with Sorted

 

Sorted Home Solutions provides full-service renovation and repair for Auckland homeowners: kitchens and bathrooms in Grade A, B and C packages, full home renovations and flood restoration, and smaller jobs such as vanity and fixture swaps. We manage all trades and the building consent process, with one point of contact from start to finish. See the kitchen and bathroom packages or the full home renovation service to start planning your project.


Sortedhomesolutions

FAQ

 

How much should I pay upfront on a renovation?

 

Master Build says a deposit should typically be no more than 10% of the residential build cost. The deposit should fund preliminary work such as plans, consents, site set-up or materials. Agree it in writing, with the reason for it, before you sign.

 

How long do I have to pay a progress payment claim?

 

If your contract does not set a different date, a formal payment claim under the Construction Contracts Act is due 20 working days after it is served on you. Your contract may set a different date, so check the payment terms you signed. If you want to dispute the claim, you must respond in writing within the deadline.

 

Do I need a written contract for a small renovation?

 

A written contract is mandatory for residential building work costing $30,000 or more including GST. MBIE recommends one for any work, whatever the size. For smaller jobs it still gives you an agreed price, scope and payment timing to refer back to.

 

Can I withhold payment if the work is defective?

 

You can respond to a payment claim with a written payment schedule that gives your reasons and the amount you will pay, and the value of the work can be reduced by the estimated cost of fixing defects. MBIE warns that simply withholding payment can make a dispute worse, so put your concerns in writing and pay the undisputed part.

 

Where do I take an unresolved payment dispute?

 

Follow the dispute process in your contract first. Claims up to $30,000 can then go to the Disputes Tribunal, and larger claims go to the District Court.

 

Sources

 